Welecome to the Grest Western (SVR) Association website.
GW (SVR) Home GW(SVR)A Background GW(SVR)A Stock List GW(SVR)A Stock List GW(SVR)A News GW(SVR)A Sales GW(SVR)A Links
 

4786 Collett bow-ended corridor Third - restoration

And so we start on our next project! In October 2018 Collett corridor third 4786 moved to Bewdley so we could make a start on its restoration.

GWR Full Third 4786 Appeal - help bring a set of GWR Bow-end carriages into service on the SVR.

 

December 2024

4786

The lining is complete on the corridor side and the transfers have all been applied. Only the garter crest with wings and arms remains to be done before varnishing. Photo: Rob Massey.

 

 

4686

The lettering going on. Photo: Dave Smith.

 

4786

Many hands make lining quicker. Corridor side. Photo: Rob Massey.

4786

Ronan at work. Photo: Rob Massey.

 

 

4786

A start has been made on lining the compartment side. Photo: Rob Massey.

 

November 2024

4786

The early stages of our ambitious project to replicate the 1922 fully lined carriage livery. Photo: Rob Massey.

4786

The wheelsets from the second bogie in finishing. Photo: Richard Herington.

4786

Bogie bearing hanger dust covers in blue. Photo: Richard Herington.

4786

Axle boxes in finishing also the rockers are on the right. Photo: Richard Herington.

 

 

4786

More progress with the lining. Photo: Rob Massey.

4786

4786

The bogie frame in finishing. Photos: Richard Herington.

4786

The main bolster painted. Photo: Mick Haynes.

 

4786

View along the compartment-side in finishing with the end fittings going-back on. Photo: Rob Massey.

 

 

1145

1145, thanks to a huge effort from Dave Massey the finishing cream is now on. Photo: Rob Massey.

 

 

4786

The gutter in finishing and lining templates being prepared. Photo: Mick Haynes.

4786

The compartment side flattened back ready for finishing. Photo: Mick Haynes.

 

 

1145

1145 now in undercoat cream after a big effort before the weather gets too cold. Photo: Mick Haynes.

4786

Looking south along the corridor side.

4786

The corridor side is in finishing brown and cream. The south end is now in finishing black and the gutters in 'half and half'. The roof is complete with just the lead capping and gangway hoods to be added. Photos: Rob Massey.

 

 

1145

1145. Much work has gone into preparing the side for painting. Most of the filler has been rubbed down ready to bring the cream panels to the undercoat stage. Photo: Mick Haynes

October 2024

4786

The gutter plates on both sides have been filled and flatted. The corridor side and north end have been flatted ready for finishing colour. Photo: Rob Massey.

 

4786

The roof is in second undercoat. It will receive a finishing coat and then the end lead capping can be fitted. The four long roof handles are back in place. These were for the carriage staff to support the installation of the destination boards. Photo: Rob Massey.

 

4786

The roof now in undercoat. Photo: Rob Massey.

 

4786

The gutter on the railway side is fitted and bedded in mastic. The town side gutters have now been welded and will be bedded in next. Photo: Mick Haynes.

 

4786

The roof is progressing well with completion of the water tanks and ventilators. The compartment side view. Photo: Rob Massey.

4786

The corridor side gutters are fully installed and the plates added and ready for welding. Photo: Mick Haynes.

4786

A close up of film star Robin with the bearing cups. Photo: Dave Smith.


 

4786

The corridor side. Photo: Rob Massey.

1145

1145. Toplights being stripped for repainting. Photo: Dave Smith.

 

September 2024

4786

The town side wooden gutters have been fixed in place with mastic sealant and the gutter plates trial fitted and their ends prepped for welding. The lower brown panels now with a coat of half and half. Photo: Mick Haynes.

 

   

4786

The gutter edges have been painted prior to the trial fitting the new gutters. Also all door locks have had the new tongues fitted. Photo: Rob Massey.

 

 

4786

The bearing spring cup supports from the second bogie under overhaul. Photo: Mick Haynes.

 

4786

From the second bogie the tie plates and cone washers have prepped and painted. Photo: Dave Smith.

 

 

1145

1145

1145. Also in the yard work has begun on the project to refresh the cream. The brown was done last summer. Photos: Dave Smith.

 

4786

The body sides are now in undercoat brown and undercoat cream is being applied. We are planning 2 undercoats and then a half and half before the final finishing. On the roof the kerbs to the water tanks have been installed and the water tanks have been tested and trial fitted. Also the ventilator pattresses are being screwed down to the roof. Photo: Mick Haynes.

 

 

 

 

4786

The bolster spring hangers and tie plates in primer. Photo: Mick Haynes.

4786

Brake block keys and bolster tie plates painted by Robin. Photo:Mick Haynes.

4786

Siphon G 1257 is also in the yard for repair work. Here Chris Amies is progressing the frame repairs beginning with repairing the standing posts. Photo: Mick Haynes.

August 2024

4786

Following two coats of primer the corridor side has a first coat of light grey undercoat. A view looking north. Photo: Gareth Price.

4786

The corridor side and south end. Photo: Gareth Price.

4786

Another view of corridor side in grey undercoat. Photo: Rob Massey.

 

 

4786

The north end in dark grey undercoat with the water tanks kerbs being trial fitted. Photo: Rob Massey.

4786

The brake block backs and hangers are now finished. The second bogie is progressing well with work at Kidderminster concentrating on the bow girders and volute springs. Photo: Mick Haynes.

 

4786

The north end and compartment side in primer. Photo: Mick Haynes.

4786

Safety straps and brake block backs from the second bogie in undercoat. Photo: Mick Haynes.

 

 

4786

The south end in grey undercoat. Photo: Mick Haynes.

4786

The corridor side flatted and mordant solution applied to the galvanised panels. Photo: Rob Massey.

4786

View of the galvanised strips pop rivetted over the roof joints. Photo: Rob Massey.

 

 

4786

The corridor side with filling complete and sanding begun. Photo: Mick Haynes.

4786

Compartment side with filling progressing well Photo: Mick Haynes.

July 2024

4786

4786 about to enter paintshop. Photo: Dave Smith.

LNER 43612 outshopped with Bewdley volunteers. Photo: Dave Smith.

 

 

4786

With the coach now in the paintshop the hoops have been removed as have all the old ventilators and pattresses. Photo: Rob Massey.

4786

All the roof hoops are being cleaned down and primed. Photo: Dave Smith.

 

June 2024

4786

The bogie overhauls continue at Kidderminster Works. The first bogie partially re-assembled. Photo: Dave Insull.

4786

Bogie bolsters reassembled. Photo: Dave Insull.

4786

A view of the centre casting and rubbing plates. Photo: Dave Insull.

4786

Bogie now with the bolsters in place. Photo: Dave Insull.

 

 

4786

4786 shunted in Bewdley yard 7th June. 4786 is due to enter the paintshop first week of July for the final body and roof repairs, this will include:

  • 2 water tanks and mounting bearers
  • Set of steel gutter faceplates
  • Timber for the gutter channel sections
  • Galvanised steel sheets for pop riveting over the joints
  • Sheet lead for the end cappings
  • Ventilators together with their pattresses

Photo: Clive Thompson.

 

April 2024

Some interesting industrial archeology revealed after the wheels have been grit blasted and spray primed. Photos: Martin white.

4786

4786

4786

4786

 

 

 

4786

Axlebox painting in progress. Photo: R Herington.

4786

Bolster spring cups being cleaned. Photo: R Herington.

 

 

Feburary 2024

4786

The compartment side stepboards now fixed in place. Photo: Rob Massey.

4786

4786

Rob Massey applying finishing black on the stepboards. Photo: Dave Smith.

 

 

4786

The bogie bearing spring for first bogie.

4786

The centre bolster with centre casting.

4786

The main bolster.

 

January 2024

4786

Some of the first bogie's rocker parts. From the left top to the bottom right are:
Bottom rocker bracket which bolts to the bottom of the centre bolster and has a "V" which supports the rocker bar.
The 2 rocker bars with 2 holes on each for the retaining split pins.
Some washers and the top rocker bracket with new rubbers - there are bolted onto the main bolster.
The bolts to attach the bracket to the main bolster.
The centre bolster supports the centre casting as part of it and is linked to the main bolster via the rocking bars.

4786

Stepboards on the compartment side.

 

 

 

 

 

4786

End view of the corridor side stepboard. Photo: Dave Smith.

4786

Corridor side stepboards prepared for fitting. Photo: Dave Smith.

4786

Corridor side stepboard viewed from south end. Photo: Dave Smith.

December 2023

Work on the first bogie is going well following the dismantling of the double bolster.

4786

The bolster slings and rocker bars painted in primer.

 

 

4786

Volute springs in finishing black.

4786

The main bolster is now stripped and ready for grit blasting.

November 2023

4786

Further bogie parts have been brought up from Kidderminster then cleaned and painted. Photo: Dave Smith.

4786

Bolster spring tie plates. Photo: Dave Smith.

 

 

4786

Parts from the bogies: fulcrum, bearing spring cup and bolster safety brackets. Photo: Dave Smith.

2426

More bogie parts for cleaning: bearing, spring hangers and bolster safety brackets.

4786

Bow girders cleaned and painted in primer. Photo: R Herington.

 

October 2023

4786

4786

At Kidderminster the bolsters have been been removed from the first bogie as well as the bearing springs and their hangers. The smaller items will be moved to Bewdley for cleaning and painting. The next job will be to dismantle the bolsters. Photos: Dave Insull.

 

 

9055

Also at Kidderminster 9055 is in the paintshop with the town side varnished. Photo: Martin White.

September 2023

4786

The first bogie stripped down in Kidderminster works. The bogie has been fully dismantled apart from lifting the bogie frame off the bolsters and the wheels.

4786

The brake block hangers are now at Bewdley for painting.

4786

A pallet of bogie parts ready for grit blasting.

 

 

4786

Bolster spring hangers after cleaning, now at Bewdley for painting. Photo: Dave Smith.

4786

Bearing spring dampers after cleaning and ready for painting. Photo: Dave Smith.

4786

Another view of one of the door headers.

August 2023

Following the trip to Kidderminster 4786 is now back at Bewdley and is now sitting on accommodation bogies while we start dismantling the original bogies for overhaul.

4786

Dave Smith has completed the signwriting on the compartment side solebar. This allows us to fit the stepboard on this side.

 

   

4786

4786 was shunted out today (14th August) and sent to Kidderminster for lifting and putting on accommodation bogies and will then be turned before returning next Monday. Photo: Rob Massey.

In preparation to move 4786 to Kidderminster to put it on accommodation bogies, we removed the wide tarpaulins and added two new ones to cover the roof and keep any rain away from the incomplete roof.

4786

4786

Halfway through changing the tarpaulins. Photos: Rob Massey.

 

4786

And with both tarpaulins in place. Photo: Mick Haynes.

4786

Completed compartment. Photo: Gareth Price.

 

 

4786

More of the external doors have been varnished and had their transfers fitted. Photo: Gareth Price.

July 2023

4786

Door No. 16 completed door panels with painted jambs and draught strips. Photo: Rob Massey.

 

 

4786

Another photo of compartment no 1 with draught strips added and door panels complete with transfers and varnish. Photo: Mick Haynes.

 

4786

The corner cappings being fitted. This completes the panelling. Photo: Rob Massey.

 

 

 

4786

Compartment door jambs being undercoated. Photo: Mick Haynes.

4786

The corridor scumbling now completed. Photo: Mick Haynes.

 

June 2023

4786

Corridor side progress. Photo: Mick Haynes.

4786

Another view of the completed corridor side. Photo: Rob Massey.

4786

The completed corridor side with destination brackets. Photo: Rob Massey.

 

 

 

 

 

4786

New linoleum laid in compartment no. 2.

1145

1145 the repaint is now finished.

1145

1145 with transfers and lettering in place.

 

May 2023

4786

Compartment no7 with new upholstery and corridor window poles in place. Compartments no6 and no5 will be upholstered next.

 

4786

Progress fitting corridor side panels. Photo: Rob Massey.

1145

Elsewhere, the Association's sales stand housed in Churchward Toplight Full Brake 1145 is being repainted. The lower panels have been painted in red oxide with grey undercoat started at the North end. Photo: Rob Massey.

 

April 2023

4786

Door frames being primed.

 

 

4786

A view along the compartment side with all panels and locks fitted.

 

March 2023 - Update

4786

Delivery of the first upholstered seats and backs. They fitted nicely paying us back for all the effort to get the seat dimensions correct! Photo: Rob Massey.

4786

Good progress with the door header furniture with half of the luncheon advert panels in place and all the headers complete. Photo: Rob Massey.

 

4786

All the top panels on the compartment side are now fully bedded and screwed and a start has been made on the lower ones. Photo: Rob Massey.

 

March 2023

4786

Most of the upper external panels on the compartment side have now been fully bedded in and screwed tight.

4786

Tapered mahogany plugs have been fitted in the door headers - 6 more to go.

 

 

4786

The picture backs and mouldings along with luggage racks and seat numbers are now installed in all compartments. Compartment no8 has typical GWR pictures added to give visitors an impression of the finished compartments.

 

February 2023

4786

The north end with most of the ironwork now in place...

4786

...and now with the weight numbers and the permitted to work over Weymouth Quay plates fitted as well.

4786

All the droplights along the corridor side are now fitted following careful adjustment so each one operates well.

 

4786

Profiling on the compartment external doors is in progress. This is to ensure the panels and pockets for the lock and the strike plates match perfectly.

4786

All 8 compartment doors have now been profiled. All the door panels have been treated and primed on their backs. Next we will fit the locks and strike plates before the panels can be bedded onto mastic and screwed for final fitting.

4786

Doors 15 and 16 are now panelled with just one final section of the cladding to go.

4786

Half of the seat numbers and brackets have been fitted.

 

January 2023

4786

4786

Two views along compartment side. The final quarterlight glasses are also fitted so the coach now has all the static glass in place. All the remaining 'G' handles on the exterior are fitted plus the two long handles at each end of the compartment side.

 

 

4786

The end steps and some of the grab handles in place.

December 2022

4786

The brackets for the small destination board and the carriage letter have been installed at both ends of the compartment side.

 

4786

All but two doors have been fitted with the brass screws to the inner steel panels to the doors and 12 of the door tread plates have been fitted.

Photos: Rob Massey.

 

November 2022 - 2

4786

The south end vestibule door is finished and rehung.

 

 

4786

Door panels to doors 9 and 10 have been fitted.

Photos: Rob Massey.

November 2022

4786

The framework repairs are nearly complete, just a few inserts to fit and trim.

4786

The door thresholds and door post angle brackets now all fitted.

4786

The Southeast vestibule door is now varnished (on the inside face) and painted (on the external face).

 

 

4786

Lino is fitted in Northeast vestibule and compartments 5, 6, 7 and 8.

Photos: Rob Massey.

 

October 2022

4786

Externally the final two new door posts for doors 15 & 16 have been fitted and external panels are now up to mid point.

4786

One of the four compartments now fitted with luggage racks, door internal panels, door side mouldings and new glazing.

4786

The communication chain tubing fitted along the corridor.

 

4786

The refitted lavatory furniture following laying the vinyl floor in both lavatories.

4786

The paper towel holder also refitted along with the toilet roll holder and the waste bin.

Photos: Rob Massey

 

September 2022

4786

The cream toilet hoppers have been treated and re-coloured bright white. We've treated two for 2426 as well.

 

August 2022 - 2

4786

4786

Compartments no's 7 & 8 are receiving their luggage racks.

 

 

4786

All the ceiling ventilators have been fixed into place.

August 2022

4786

Compartment no. 6 progressing with new tongue & grove paneling along the external wall.

4786

Compartment no. 8 prepared for the seats and seat backs to be upholstered.

4786

The corridor window mouldings reinstated.





 

4786

Door no. 11 and framework repairs between doors 11 and 12.

4786

Further progress on the compartment-side door no. 11 now re-hung and the panelling progressing.

4786

North end lavatory ready for the new vinyl flooring cover.

 

 

July 2022

4786

Door no. 10 is now rehung and fits well.

4786

The frame repairs between doors no. 10 and 11 are progressing well.

4786

First set of dolly switches in place and the dimming system is operational.

 

4786

The south end lavatory hopper window complete with cover.

4786

The south end lavatory in place with flush cover stained and varnished.

 

 

July 2022

4786

Framework and cantrail repairs are continuing. The section between compartments 9 and 10 is nearing completion. The facing section to the cantrail should be added soon and the top panel is ready to be fitted.

4786

The south end lavatory with flush valve cover fitted.

4786

The stepboard corridor side is now painted.

4786

2999 is still with us and seen here crossing Oldbury Viaduct. Photo: David A Smith.

 

4786

Compartment no. 6 with picture backs and cornices in place.

4786

Compartment 5 ceiling now in finishing coat - the last one.

4786

Pete Simpson's Riding Van 89 of 1908 has now passed to the Association and we've been cleaning and sorting in preparation for use as our mess van. Photo: David A Smith.

 




 

 

June 2022

4786

The repairs to the final section of cantrail are underway.

Black Country Steam

And congratulations to Paul Dorney from the restoration team on the publication of his book 'Black Country Steam' published by Pen & Sword. It is strongly recommended!

 

 

4786

Compartment no. 5 with the final ceiling panel in place.

4786

Compartment no. 7 with the ceiling painted.

4786

2999 leaving Bewdley. Photo: David A Smith.

May 2022

4786

Fitting the final roof edge has been completed. The clamps are supporting the repairs to the face of the cantrail and the old steel screws have been drilled out to remove any chance for further splitting. Photo: Rob Massey.

4786

...the cantrail with the clamps removed. Further repairs are still be needed here and will be tackled next.

 

 

4786

The lavatory seat at the north end with its supporting bracket. The seat lids with be tackled next.

4786

The coat handles and the gentleman’s 'steadying' handle in place.

 

April 2022 - 2

The ceiling in compartment No 1 with lamp reflectors and bulbs installed.

 

4786

4784

The stepboard for the corridor side has now been completed and trial fitted. This will be painted next and then permanently fitted. This has been made from Douglas Fir so hopefully will be long lasting.

 

April 2022

4786

4786

Compartment No. 1 with ceiling complete, pictures and mirror in place.

4786

The distant switch in corridor.

4786

Roof edge repairs - just 3 sections to go.

 

 

 

 

 

 

 

4786

Compartment doors now being fitted with the exterior panels.

4786

Painting the solebar dimensions is complete thanks to Dave Smith, enabling us to commence the stepboards on the corridor side.

4786

View along the corridor with all door panels now fitted.

4498 on test passing through Bewdley station. Photo: Bob Massey.

March 2022 - 2

4786

The remaining sections of roof edge are being cut away.

4786

The roof edge fitted on second section of new cantrail.

4786

Removing the last of the old panels on the compartment side.

 

 

4786

4786

Picture backs cornice and ceiling being finished off in compartment no1.

4786

South-end lavatory being fitted - this will be changed to white.

 

March 2022

4786

The door headers are being installed by Paul as part of our concentration on completing the door fitting. He has fitted 7 out of the 8 on the corridor side do far.

4786

Door header in place.

4786

The flush valves are being trial fitted in the 2 lavatories. It is important to get the position just right for them to work properly. We are expecting the new soil pipes imminently and then we can be sure they work correctly.

 

4786

The new section of replacement cantrail fixed in position. Photo: Rob Massey

4786

In compartment 8, the outer ceiling panel with beading, cornice and anti dust moulding.

4786

Door 10 assembled - just one more to go.

 

Photos: Mick Haynes.

 

February 2022

4786

The internal panel has been fitted on door no.3, on the corridor side. Door no.2 is also fitted and door no.1 will be next.

4786

Our new Greenhouse:) We will use this for painting and varnishing. Hopefully it will survive the storms.

Elsewhere the underframe painting is nearing completion with most now in chassis black, the gutter plates are being filled, flatted and re-primed to ensure a smooth finish, and the levelling of the floor in the corridor is progressing well and the tops of the body bolts will be next.

 

4786

The North-end Lavatory Door is now installed.

4786

The south-end lavatory beading is fitted and the walls patch filled, flatted and re-primed. Here's Robin admiring his handy work!

 

January 2022 - 2

4786

The door is now fitted to north end lavatory.

4786

All but one of the roof hoops have been tied in to the new cantrail.

4786

The south end lavatory is receiving its tiles and the washbasin is in place.

 

 

4786

Trial fitting of the steel door panels, this will be finished in mahogany colour. Also Door 11 has been assembled and glued and door 13 taken off and disassembled ready for the usual repairs.

4786

Cleaning and painting of the trussing is progressing well.

4786

The transoms between trusses. Also Dave Smith is preparing to sign write the solebar which will in turn enable us to start fitting the stepboards.

 

January 2022

Our Best Wishes for 2022!

You'll see from the photos that both lavatories are making good progress. Elsewhere we've been cleaning off the gutter plates and cleaning the underframe trussing. Door 5 received its panel meaning that all doors on the corridor side are fitted and work!

The internal door panels are being painted in undercoat brown whilst fitting the garnish panels and the panel supports has begun. We are using door 10 for trial fitting.

On the compartment doors the repairs to the parts for door 11 are nearing the time when assembly can be contemplated and door 9 is close to final adjustment.

4786

The first new garnish rail fitted on door no. 10

4786

Progress with the south end lavatory support mouldings.

 

 

 

 

 

4786

The North end lavatory now with walnut scumbling and pelmet and window mouldings in place.

4786

Lavatory corner where the hopper will be installed.

4786

Close up of the lavatory hopper ventilator.

 

 

December 2021

4786

The North end lavatory has been brought up to finishing coat.

4786

Ceiling beading now in place.

4786

New panelling in compartment No. 1.

4786

The solebar is being painted after stripping to bare metal.

 

4786

The new cantrail looking towards the end - another long section will go in to replace the rotten wood on the left.

4786

New gangway canvass being fitted.

 

Photos: Mick Haynes

November 2021

4786

The south end lavatory framework repairs, on the compartment side, are progressing well.

4786

The first lavatory is now in undercoat.

 

 

4786

The north end gangway is being prepared for its canvass.

 

Photos: Bob Massey

 

October 2021

4786

The first side panel fitted on the compartment side.

4786

Chris helping Dave Smith with the solebar - a rare photo:)

 

4786

New tarpaulins are fitted, these give much more light while working beneath.

4786

The gutter plates ready for cleaning.

4786

The solebar date stamp shows the underframe was constructed in September 1925.

 

August 2021

4786

Mike Walker has now completed the framework repairs to the north end and the end panels are now on. Rob has fixed them on permanently and installed the gangway brackets.

4786

Mike Walker is making great progress with the north end toilet frame. Photo: Rob Massey.

 

 

 

 

 

 

 

4786

We have completed installing the ceiling panels up to compartment 7 and are working on compartment 8. Some of the ceiling pattresses are also installed.

4786

Trial fitting of the picture frames.

4786

Now the corridor doors are hung we have begun to work along to fine tune each door to profile and to ensure that the private locks and 'V' plates are all present and fit.

 

June 2021

4786

4786

Ceiling in place in compartment no 1 with picture panel.

The ceiling team happy with their work in compartment no 1!

4786

The corridor connection has been removed from the north end and repairs begun.

4786

Corridor connection frame waiting repairs.

 

4786

The varnishing of the compartment doors is complete. Here's sliding door no 8 viewed from the corridor side...

4786

...and from the compartment side.

 

 

Photos: Mick Haynes

June 2021

4786

Scumbling on corridor wall.

4786

View along corridor.

4786

New ceiling panels being primed.

4786

View of the steam heat pipe and tank filler pipes.

4786

Richard applying paint to the back of a compartment D panel.

 

4786

External doors being prepared for hanging.

4786

Another view of the external doors.

4786

Doors 13 and 15 opened and in reasonable condition.

4786

View of the work required on the framework - the pillar is OK but...

 

April 2021

At long last we are almost fully back at work!

4786

Tuesday 30th March saw a major shunt to rearrange Bewdley yard and released 4150 in preparation for its move to Bridgnorth.

Together with the LNER SVR Coach Fund's GWR Wheelchair and Buffet project 9581, 4786
was tripped to Kidderminster to be turned on the turntable. Photo: Richard Herington.

4786

The compartment doors are being varnished.

 

4786

The regulator cupboard wiring nears completion and is being prepared for scumbling.

4786

With the now coach turned, the poor condition of the cantrail on the no. 1 end of the compartment side can be accessed and is being prepared for repair.

January 2021

4786

The seat bases are progressing well. The extensions to their front rails are complete and work has begun to tie the springs into position. Photo: Richard Herington.

 

   
December 2020

After another pause we're back at work now.

4786

4786

The regulator cupboard doors are back in situ after painting with satinwood scumble.

 

 

4786

4786

All but two seat backs and bases have been trial fitted before upholstering.

 

July 2020

With lockdown easing, progress is picking up again.

4786

The south end vestibule including rail.

4786

Lower part of vestibule scumbled.

4786

Door 3 repaired.

4786

The vestibule including the distant switch cupboard.

 

 

 

4786

The newly installed gangway canvas. Photo: Bob Massey

4786

New seat backs being made.

4786

Repairs to compartment partition in progress.

4786

Door closers for 6045 and mirror frame for 4786.

Photos: Mick Haynes

 

 

March 2020

4768

The overhauled suspended gangway frame in position.

4768

The north end vestibule ceiling and coving.

4768

Door headers under repair.

4768

A batch of corridor hand rail brackets cleaned and polished.

 

4786

New wash basin supports.

4768

A view along corridor towards the distant switch.

4768

The south end toilet floor.

Photos: Mick Haynes

January 2020

4786

The gangway frame with new bottom angle and receiving weld repairs to corrosion pitted areas.

4786

The corner post repairs completed.

4786

The top and left side end panels trial fitted.

 

 

 

 

4786

The vestibule ceiling panels fitted and filler applied.

4786

The vestibule ceiling complete with pelmets fitted.

4786

All the picture frame panels are fitted – this is a new one with a new picture installed.

Photos: Bob Massey

 

December 2019

4786

A view along the completed corridor framing and panels.

4786

Some of the completed droplights.

4786

Wiring in place for the Distant Switch Cupboard.

 

 

4786

All 9 window frames and glass now installed.

4786


Components for new seat backs.

4786

A view of the vestibule ceiling.

4786

A view of the painting area in coach no 98 containing a toilet base and two small destination boards.

Photos: Mick Haynes

November 2019

On 4786 the corridor side framework repairs are complete and work has begun to repair the north corner post. We will shortly fit new glass to all nine of the large corridor windows. Work has begun on repairs to the external doors.

4786

Newly painted underframe and the steam heat piping installation.

4786

Some of the external doors for 4786 under repair.

4786

Toilet tiles at the south end cleaned or replaced.

 

4786

View of the new corridor ceiling panels.

4786

View looking along the corridor from the north end where there's still ceiling panels to fit.

4786

Trail fitting of the seat back and base - they fit well.

Photos: Mick Haynes

October 2019

4786

More of the compartment frames have been fitted.

4786

Repairs have begun on door no. 1.

4786

Corridor ceiling being fixed into place.

 

4786

The first of the new radiator castings.

4786

Work has begun on stripping the toilet at the south end.

4786

Tiles being fixed in north end toilet.

September 2019

 

4786

Newly repaired framework, corridor side.

4786

New ceiling in north end toilet.

 

 

4786

Trial fitting of seat back and panelling.

4786

New photo frames being made and fitted.

4786

Rewiring in progress along the corridor ceiling.

 

August 2019

 

4786

View along the corridor receiving base colour.

4786

View along the corridor with new cantrail and roof edge.

4786

The rotten cantrail before replacement.

4786

New cantrail fitted.

4786

Roof edge fitted.

 

 

4786

Newly built regulator cupboard installed.

4786

The new battery box is now fixed into position.

4786

Ceiling panels ready to be fitted.

4786

More progress with the seating.

4786

Tiles being cleaned down.

 

Photo: Mick Haynes

June 2019

Despite the recent weather we're making good progress!

4786

The inward face of the vestibule door.

4786

The exterior of the vestibule door.

4786

Another seat base ready for modification.

Photos: Mick Haynes

 

4786

More new roof edges - just three remaining on the corridor side to complete.

4786

The new picture frames in compartment no1.

4786

The hole where the larger roof tank was.

4786

Brake shaft and vacuum cylinder brackets being painted.

May 2019

4786

The first four roof panel edges have been fitted to the South end of the coach.

4786

The next three sections have been cut away for cantrail repairs. Framework repairs and new galvanised panels are completed from door 4 onwards.

 

 

4786

4786

The North end framework exposed. The cantrail is rotten and will be replaced but the corner post is sound.

4786

All the corridor side doors now open but there much still to do to bring them up to standard.

Photos: Robert Massey

April 2019

4786

Cantrail repairs underway on the riverside of the coach...

4786

...with the first of the new roof edges fitted.

 

4786

Dave making adjustments to another seat base.

4786

The two Brian's at work on internal droplights.

 

March 2019

Work has concentrated on the body framework and panelling as well as the compartment doors and seats.

4786

View along the corridor side showing we have reached between door 5 and 6.

4786

Window 6 framework repaired.

4786

The new battery boxes receiving paint.

 

 

Photos: Mick Haynes




 

4786

Compartment door now ready for rehanging.

4786

Another seat base being modified.

4786

Compartment 8 sliding door.

4786

Compartment panel and internal droplights under repair.

February 2019

4786

Body repairs in progress along the compartment side.

4786

Window no. 8 frame repairs progressing well.

4786

A compartment sliding door repaired...

4786

...with another compartment door under repair.

4786

First of the new battery boxes near completion.

 

4786

New end panel cutout and trial fitted.

4786

Close up of the end panel.

4786

Compartment view towards the corridor.

4786

Lock-side post to carry door no. 7 removed for renewal.

 

Photos: Mick Haynes.

January 2019

4786

Stripped mahogany panelling and window mouldings in compartment five.

4786

View along full length of corridor, painting of compartment sides complete.

4786

Stripped north end vestibule door.

 

 

4786

Corner plates fitted to the repaired framework.

4786

Exterior view of the repaired framework.

4786

Interior view of corner plates and new window mouldings.

4786

Repaired stringer above the headstock.

 

Photos: Bob Massey

 

December 2018

4786

A view along the corridor showing progress.

4786

The south end vestibule has cleaned up well.

4786

A modified seat back and base being trial fitted.

4786

The repairs to the framework have begun.

 

Photos: Mick Haynes


 

 

 

 

 

 

 

 

 

 

 

 

4786

The corner post is in good condition.

4786

A view along the new scaffolding.

4786

A kit of parts for the battery box.

4786

A view along the corridor of the last sections still to be stripped.

 

November 2018

The work on 4786 has started well. We are working mainly on the corridor side starting from the south end. Much of the framework is in good order, except for the bottom stringer which will need repair along with replacement of all the body brackets. The doors are also good only needing repairs to the lower part of the jambs.

We are currently stripping off the layers of paint, and trial fitting the seats. Our plan is to clean off, repair and refit as we move along as the coach is fairly complete and it will save us storage space. A working platform will be erected during the coming week.

4786

A view along the corridor after cleaning and tidying up.

4786

A view of the south-west corner after the external panels have removed ready to repair the frame-work.

4786

We are trial fitting the seat backs and bases before re-upholstering.

 

Photos: Mick Haynes

 

4786

We've ordered a regulator cupboard to fit in here.

4786

The south-west vestibule the end panels have been removed.

4786

The toilet doors are sound...

4786

...but the toilet compartment needs some work!

 

October 2018

4786

4786

4786 shunted into position at Bewdley. The coach will be covered with new transparent tarpaulins. Initially we will remove the external panels to assess the work to be done.

 

Photos: Dave Smith.

 

4786

4786

4786

A few views of the interior, a surprising amount of the original has survived.

 

 
4786
Home | Background | Stock List | How To Help | News | Sales | Links
© 2006-2022 GW(SVR) Association. Page last updated: 15 December, 2024 Webmaster